When standard off-the-shelf transformers don’t fit your application, a custom design is the answer. But designing a custom transformer from scratch can seem daunting—what information do you need? How does the process work? What can you expect from a magnetics supplier?
This guide walks through the complete custom transformer design process, from specification to production.
Shaanxi SiRui Technology Co., Ltd. designs and manufactures custom transformers and inductors for power electronics applications. Contact: sales@sirui-tech.com | Web: www.sirui-tech.com
1. What Information to Provide
- Topology: buck, boost, flyback, LLC, forward, line frequency
- Input voltage range: e.g., 90–265 VAC or 400 VDC bus
- Output voltage and current: e.g., 12 V, 5 A
- Power level and switching frequency
- Isolation requirement: e.g., 3 kV, 4 kV reinforced
- Mechanical constraints: max dimensions, mounting style
- Ambient temperature and target efficiency
- Safety standards: IEC 60601, UL, IEC 60950
2. Design Process Steps
- Specification review: manufacturer reviews and flags constraints
- Core selection: material and shape based on frequency, power, size
- Turns calculation: based on voltage ratio and target flux density
- Wire sizing: round wire, litz, or foil based on frequency and current
- Loss calculation: core loss + copper loss, verify efficiency target
- Thermal check: verify temperature rise within insulation limits
- Prototype build: 5–20 pieces for your testing
- Testing and iteration: you test in application, request changes
- Production qualification: tooling, test procedures, qualification batch
- Mass production: 100% tested units
3. Typical Timeline
| Phase | Duration |
|---|---|
| Design and quotation | 1–3 days |
| Prototype build | 1–2 weeks |
| Testing and iteration | 2–4 weeks |
| Production qualification | 2–4 weeks |
| Total to mass production | 4–8 weeks |
4. Common Mistakes
- Incomplete specification: missing frequency or isolation data delays design
- Unrealistic size requirements: 100 W in a 20 mm cube
- No prototype testing: assuming calculations are perfect
- Ignoring EMI: transformer design heavily affects conducted EMI
- No efficiency margin: target 97%, design for 98%
5. Sirui-Tech Custom Design
- Free design review and quotation within 1–3 days
- Prototypes in 1–2 weeks
- Full test report with every prototype batch
- 100% production testing: L, DCR, hi-pot
- Experience: transformers, inductors, CMCs, current sensors
Conclusion
Designing a custom transformer is a collaborative process. Provide a complete specification, test prototypes thoroughly, and allow enough time for iteration. A well-designed custom transformer outperforms any off-the-shelf solution.
Need a custom magnetics design? Contact Sirui-Tech at sales@sirui-tech.com with your application requirements—free design review and quotation.
Related custom-design guides
Construction, testing and application guides
More on sourcing and specifying magnetic components
- Incoterms 2020: who owns the risk and the cost
- Estimating temperature rise before you order
- Insulation class A to H: what it costs
- Copper vs aluminium windings
- What must be on a test report
- Tariffs, origin and trade remedies
- Comparing three quotes for the same part
- Low volume without prototype pricing
- Why lead times change
- The cost of poor quality